Skip to Content

Northwood Cemetary

Job Scope

26,000 SQ Yards of milling with 2,600 Ton of Surface course. Additional is about 1,200’ feet of berming and additional 350 ton of base repair.

  • 26,000 square yards of milling
  • 2,600 tons of surface course
  • Approximately 1,200 feet of berm
  • Additional 350 tons of base repair

Special Details

This project was very important to maintain communication with the city and management on schedule in order to work around funerals. Work had to stop or be scheduled around Funerals. The project suffered from a bad subbase and required the use of smaller trucks and to then not utilize streets as they were paved. Large trucks were only allowed on streets that were unpaved. Once they were paved we did not drive loaded dump trucks on them due to structural issues. Cleanup was another big issue as we had to maintain clean and drivable surfaces as this cemetery would experience about 100-200 walkers, runners and visitors to the site daily.